Activity description

List of construction activities:
 

  • Site cleaning
  • Bore well digging
  • Site Marking
  • Sump construction
  • Soil digging for sump
  • Sump Construction
  • Foundation digging
  • Pillars
  • Paya
  • Start carpenter work
  • Pillar base
  • Pillars until Plinths
  • Stone Foundation in paya
  • Plinths beam
  • Fill soil inside Plinths.
  • Filling cement and 40 MM Jelly on top of Soil -- this will be done inside plingth area
  • Setting up main door frame and other room door frames
  • Wall construction until window frame base
  • Setup all window frames based on its sizes until 7 feet from the floor
  • Setup lintel and saja
  • Wall construction until beams
  • Setup kitchen ventilator and bathroom ventilators
  • Sheet centring for beams and also roof
  • Fix sheets based on water level
  • Apply plaster for the gaps between sheets
  • Apply oil for sheets
  • Bar bending work for beams and roof
  • Inverter beams
  • Electric pipes setup inside roof
  • Molding
  • Storing water on top of the roof
  • After 18 days remove sheet centring
  • Hocking for the roof if not done for the pillars
  • Electric pipes
  • Clear any blockage in the roof pipes
  • Laying electric pipes in the walls and setup electric boxes
  • Plumbing work for kitchen and bathroom
  • Setup water pipes and sewage pipes till outside of the wall
  • Setup Indian latrine if you are going with this option
  • Water proofing for bathrooms
  • Close all water and sewage pipes with temporary caps
  • Setup kitchen platform and sink
  • Tiles laying in bathroom and kitchen for walls
  • Plastering of roof and walls inside
  • Plastering of outside walls
  • Applying putty for window frames
  • Fixing window frames
  • Granite Lying
  • Granite tiles Laying in bathroom if you are going with this option
  • Fixing bathroom fittings
  • Finishing outside plumbing work and tank
  • House Elevation
  • Painting
  • White wash inside house two cotes
  • Applying putty for internal walls
  • Apply one paint coating inside
  • Apply primer outside
  • Electric work
  • Electrical wiring
  • Dummy plate fixing/ electrical holders
  • Electrical switches setup
  • Apply paint coating outside
  • Laying electric service wire from pole to meter board
  • Fixing meters in panel board.
  • Digging pit for power earth
  • Digging pit
  • Motor & connection to tank
  • Parking tiles
  • Compound wall
  • Sewage lines to pit